Uckfield Shepards Way

Uckfield Ridgewood
Remove existing conservatory and build new rear extension to form area for children and utility extension.
December 18 to March 18

Again we would like to personally thank Mr & Mrs Brown from all at MJS Developments as you were also fantastic to work for.

These clients opted for MJS to carry out all the professional paperwork, we again used our architect, structural engineer, etc to do there specific roles.

Once all was in place in August 18 we confirmed a date to start which was November / December 18.

When we arrived we had to remove an existing conservatory, all of the existing sandstone and concrete patio slabs as these were to be lifted carefully and re laid at the end, we dug out the footings and removed waste in our company vehicle as there was no space for a skip this was done per load, we also had to remove a small drain and waste pipe and install new inspection chamber so this was outside the boundary of the new building, we then had the concrete delivered to site and built up to DPC and done the over site before we broke up for Xmas.

We then built the cavity walls, cut and pitched the roof, supplied and fitted 2 large VELUX roof windows 1600mm x 1200mm, carried out roof tiling and all the lead work, put in a full length cavity tray, 2 large windows that faced the garden and large set of french doors, we carried out all the electrical works and called in our gas safe engineer to re route the boiler flue so it complies with regulations, ran in plumbing for 2 1400mm wide type 22 radiators, we done the plaster boarding, plastering, built a new stud wall to extend utility area, supplied and fitted laminate flooring, skirting etc and left ready for the clients to carry out decoration as they see fit.

We re laid the sand stone slabs to the side and to area in front of the french doors.

We left the property and garden are all clean and tidy.